11kV Stane Park Electrical Infrastructure Project – Essex

MD Groundworks successfully delivered the full design and installation of HV and LV electrical systems for the Stane Park Retail Development. Acting as a specialist subcontractor, we completed the 10-month project on time and within budget, supporting the delivery of 10 commercial retail units with reliable and sustainable power infrastructure.

Project Overview

Location: Stane Park, Essex

End Users: 10 Commercial Retail Units

Duration: 10 months

Scope: Full HV/LV Electrical Infrastructure Installation

DNO: UK Power Networks

Scope of Work

MD Groundworks was responsible for the end-to-end delivery of electrical infrastructure, including:

  • Design and installation of an offsite 11kV cable route (approx. 2km)
  • Construction and fit-out of a dual-transformer substation
  • Full HV and LV cable terminations
  • LV cable distribution across the development to meter points and service heads
  • Integration with UKPN’s primary substation

Offsite HV Cable Installation

We delivered a high-quality, DNO-compliant installation of 2,400 metres of 11kV high-voltage cable connecting the site to UKPN infrastructure. Key deliverables:

  • Trenching: 450mm wide x 900mm deep
  • Ducting and reinstatement of the public highway to HAUC standards
  • Completion of 7 joint bays with cables installed at 250m intervals
  • Zero sheath damage and full cable integrity throughout

Onsite Substation Construction

Our experienced electrical and civil teams constructed and commissioned the on-site substation, including:

  • Installation of dual 11kV transformers
  • HV and LV switchgear configuration
  • All necessary cable terminations and testing
  • Energization and handover in accordance with UKPN guidelines

Sustainability & Logistics

The project was supported by our Wickford depot, located just 40 minutes from site, allowing:

  • Reduced carbon emissions through efficient material transport
  • Lower fuel use and minimal environmental impact
  • Rapid deployment of tools, plant, and materials

Project Outcomes

The Stane Park project was successfully delivered to the satisfaction of all key stakeholders, including:

  • The main client
  • UK Power Networks
  • Essex County Council

MD Groundworks demonstrated expertise in electrical infrastructure installation, substation construction, and HV/LV cable works, reinforcing our position as a trusted electrical and groundworks subcontractor in Essex and the South East.